| Home | Industry Relations | OEB Key Initiatives | Farm Stray Voltage (EB-2007-0709) |
Farm Stray Voltage (EB-2007-0709)
On June 22, 2007, the Board received a Directive from the Minister of Energy that requires the Board to implement such measures as the Board considers necessary to address the issue of stray voltage as it affects the farm sector.
In response to the Minister’s Directive, the Board conducted a consultation process to solicit input from interested parties regarding stray voltage, its potential impact on the farm sector and the identification of measures that could be implemented to mitigate this impact.
Note: Information contained in minutes, notes or other documents of the Farm Stray Voltage Consultative Group, including presentations made to the Consultative Group, represents the views of the individuals participating in the Consultative Group meetings only, and in no way reflects official Ontario Energy Board position or opinion.
DOCUMENTS
| Date | Update | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| Sep 24-09 |
The Board has issued its Decision and Order on Cost Awards in respect of this initiative. |
||||||||
|
Aug 4-09 |
Cost claims have been received from eligible parties and transmitted to those licensed electricity distributors from whom costs awarded will be recovered. |
||||||||
| Jul 10-09 |
The Board has issued a Notice of Hearing for Cost Awards. Key dates in the Notice: eligible parties' cost claims are due July 31, 2009; distributor objections, if any, are due August 14, 2009; and eligible parties' reply submissions are due August 21, 2009. |
||||||||
|
Jun 16-09 |
The Board has issued a Notice of Amendment to a Code in relation to the Farm Stray Voltage Consultation (EB-2007-0709). The amendments to the Distribution System Code include the addition of a ‘Farm Stray Voltage Distributor Investigation Procedure’ as Appendix H to the Code.
|
||||||||
|
May 4-09 |
Written comments received on the Board’s Notice of Proposal to Amend a Code posted on March 31, 2009 are provided below. |
||||||||
|
Today the OEB issued a Notice of Proposal to Amend a Code in relation to the Board’s Farm Stray Voltage Consultation (EB-2007-0709). The proposed amendments to the Distribution System Code consist of a Farm Stray Voltage Distributor Investigation Procedure. As explained in the Notice, comments on the proposed amendments must be filed by April 30, 2009. |
|||||||||
|
Dec 11-08 |
Written comments received on the Board’s Notice of Proposal to Amend a Code posted on October 31, 2008 are provided below.
|
||||||||
|
Dec 3-08 |
The Board issued a Decision on Cost Eligibility in relation to the Board’s Notice of Proposal to Amend a Code, posted on October 31, 2008. The request for cost award eligibility is provided below. |
||||||||
|
Oct 31-08 |
Today the Board posted a Notice of Proposal to Amend a Code in relation to the Board’s Farm Stray Voltage Consultation (EB-2007-0709). As explained in the Notice, comments on the proposed amendments to the Distribution System Code set out in the Notice must be filed by December 5, 2008. |
||||||||
|
Jul 25-08 |
Written comments received by the Board on the Board staff Discussion Paper Farm Stray Voltage: Issues and Regulatory Options are provided below.
|
||||||||
|
Board staff has prepared a Discussion Paper entitled Farm Stray Voltage: Issues and Regulatory Options aimed at eliciting written comments from all interested parties. As explained in the Cover Letter, all interested parties are invited to send written comments to the Board Secretary by July 11, 2008. Also posted are three reports prepared by expert consultants at the request of Board staff.
En francais:
French translations are provided for information purposes only. In the event of an inconsistency between the English and French versions, the original (English) version takes precedence. |
|||||||||
|
Jan 30-08 |
The Farm Stray Voltage Consultative Group met on January 22, 2008. Meeting Notes summarizing the discussions are provided below. |
||||||||
|
Dec 12-07 |
Presentations given at the Farm Stray Voltage Stakeholder Consultation Conference on Dec. 5, 2007.
French translations are provided for information purposes only. In the event of an inconsistency between the English and French versions, the original (English) version takes precedence. |
||||||||
|
The Board issued a Supplementary Decision on Cost Eligibility. The Farm Stray Voltage Consultative Group met on November 30, 2007. Meeting Notes summarizing the discussions are provided below. |
|||||||||
|
Today the Board posted a letter inviting participants and all interested parties in the Farm Stray Voltage Consultation (EB-2007-0709) to an upcoming Stakeholder Consultation Conference on December 5th, 2007. |
|||||||||
|
Farmer Consultation Meeting Schedule – Oct. 29th through Nov. 9th.
The Farm Stray Voltage Consultative Group met on October 19, 2007. Meeting Notes summarizing the discussions are provided below. |
|||||||||
|
The Board decision on cost eligibility in relation to the Farm Stray Voltage Consultation was issued on October 11, 2007. Requests for cost award eligibility are provided below under the Update for Aug. 31, 2007. The Farm Stray Voltage Consultative Group met on September 25, 2007. Meeting Notes summarizing the discussions and a copy of the presentation to the group by a representative from the Public Service Commission of Wisconsin are provided below.
|
|||||||||
|
The Board has posted requests for cost award eligibility in relation to the Farm Stray Voltage Consultation. Requests for cost award eligibility:
The Farm Stray Voltage Consultative Group met for the first time on August 17, 2007. The Board has posted a summary of the discussions.
|
|||||||||
|
Today, the Ontario Energy Board (the Board) issued a letter inviting interested parties to participate in a consultation on farm stray voltage. This consultation is in response to a Directive issued to the Board by the Minister of Energy. |
CONTACT
For further information regarding the Farm Stray Voltage Consultation, please contact Stephen Cain at (416) 544-5162 or by email at stephen.cain@oeb.gov.on.ca. The Board's toll-free number is 1-888-632-6273.